How Long Does It Take To Remodel A Kitchen?

The average full kitchen remodel takes 3-5 months to complete. An exact estimate will depend on a few factors, including demolition, size of the kitchen, custom designs and service.

How Long Should A Kitchen Remodel Take?

A kitchen remodeling project can be a long but rewarding process. Generally, most remodels will follow the same steps and timeline overall. Let’s take a look at the most common stages of a kitchen remodel.

Step 1. Finding A Kitchen Remodel Contractor

Feel free to reach out to several contractors ahead of time to get the best estimate to fit your budget. Contractors can help you find the right materials, styles and designs for your kitchen. The good news is most services will offer a free in-home estimate. Contact the team at Urban Customs for more information!

Step 2. Materials And Design

After selecting a contractor to take on this task, you can start planning your vision for the new and improved kitchen area. Ensure you cover all aspects of the remodel. This includes paint, lighting, tables, countertops and vanities. Keep in mind that you may have to get remodeling permits ahead of time, depending on your location. You should also order any special materials in advance of the remodel. You can always contact the designer to help you maximize your kitchen space.

Estimated Timeline: 3-4 Weeks.

Step 3. Demolition

The demolition portion of the remodel will be the most time-consuming part of this project. Depending on specific needs and features, this can take up to a few months. Demolitions can include anything from flooring removal to replacing cabinets, countertops and appliances. Make sure to turn off the electricity before the demolitions begin.

Estimated Timeline: Several Months.

Step 4. Installation

Installations will start as soon as the kitchen area has been completely demolished and cleared. Essential fixtures, such as HVAC systems, plumbing and electric, can take under a week to install. Flooring is typically the next installation project for contractors. Cabinets and countertops are installed once the flooring is secured.

Estimated Timeline: 1-2 Weeks.

Kitchen Remodel Schedule

What should your kitchen remodel schedule look like? Here is a quick example.

Week 1:

  • Demolition
  • Dust and floor protection
  • Straighten and level framing

Week 2:

  • Electric
  • Plumbing
  • Duct work
  • A/V wiring

Week 3:

  • Inspections
  • Install insulation
  • Stock drywall

Week 4:

  • Sand and prime drywall
  • Hang and finish drywall

Week 5:

  • Install flooring
  • Receive and set cabinets

Week 6:

  • Interior trim work
  • Measure for countertops

Week 7:

  • Install countertops and appliances
  • Trim out electric and plumbing

Week 8:

Week 9:

  • Painting

Week 10:

  • Professional cleaning service
  • Final walkthrough

Arizona Kitchen Remodel Estimates

If you are searching for “Kitchen Remodeling Near Me“, “Kitchen Remodeling Companies“, “Kitchen Remodeling Contractors Near Me“, or “Kitchen Remodeling Phoenix Arizona“, Urban Customs can help!

Our kitchen remodeling contractors service the entire Phoenix Valley Area, including Phoenix, Gilbert, Glendale, Peoria or anywhere else in the Valley of the Sun. Give us a call today at 480-747-2516 for a kitchen remodeling estimate.